Construction Update: Week of 04/03/26

  • Apr 3
  • 1 min read

Friday, April 3, 2026


Dear Neighbors,


Welcome back to another update on the Mountain View Lot 12 project. We continue to make steady progress on site.


Throughout the week, we have been excavating the final subgrade of the mat foundation and elevator pits. We are expecting to wrap the bulk of the offhauling this week. We also started lime treatment of the subgrade dirt, which helps stabilize and strengthen the dirt prior to starting mat slab rebar activities.


Next week, we will start installing underground plumbing and electrical pipes and continue with onsite storm drain pipe installation. Lastly, you may notice delivery of rebar and the beginning of mat slab formwork.


We hope these updates are helpful in keeping you informed about what’s happening onsite. For the latest updates, please visit the Project website at www.mountainviewlot12.org


Thank you for your patience while this work is underway and please reach out to me with any questions about ongoing operations. 


Contact Information:

Name: Christian Blevins

Phone: 408-462-2407

 

Best regards,

Christian Blevins

Assistant Project Manager

Related California Construction

 

P.S. If you received this via Wix Blog email notification and would like to unsubscribe, click the ‘unsubscribe’ link at the bottom of your email. And if you were forwarded this message and would like to be added to our mailing list, please visit the homepage at www.mountainviewlot12.org and submit the contact information form.

 
 

Alta Housing and Related California are equal opportunity housing providers and employers, dedicated to diversity, equity, and inclusion regardless of religion, sex, gender, national origin, disability, race, age, marital status, or sexual orientation.  

bottom of page