Construction Update: Week of 04/06/26
- Apr 10
- 1 min read
Friday, April 10, 2026
Dear Neighbors,
Welcome back to another update on the Mountain View Lot 12 project.
This week, we started to layout and install underground plumbing and electrical pipes on the south side of the project. Carpenters also started to deliver material and began assembling formwork for the mat slab. Both activities, including formwork installation, will continue into next week as part of the mat foundation. In the meantime, we are expecting to wrap up onsite storm drain work along the west side of the project.
Next week, we also plan to start offsite storm drain and water utility work on California street. This activity is expected to take several weeks and will require traffic control on California Street. Please be cautious of slower traffic speeds and consider other traffic routes if possible.
We hope these updates are helpful in keeping you informed about what’s happening onsite. For the latest updates, please visit the Project website at www.mountainviewlot12.org
Thank you for your patience while this work is underway and please reach out to me with any questions about ongoing operations.
Contact Information:
Name: Christian Blevins
Phone: 408-462-2407
Best regards,
Christian Blevins
Assistant Project Manager
Related California Construction
P.S. If you received this via Wix Blog email notification and would like to unsubscribe, click the ‘unsubscribe’ link at the bottom of your email. And if you were forwarded this message and would like to be added to our mailing list, please visit the homepage at www.mountainviewlot12.org and submit the contact information form.