Throughout this week, we started to install walls on the north side of level 2 and the south side of level 3. We are expecting to start floor joists for level 3 north and level 4 south in the next week. In addition next week, we will start to frame walls on the south side of the 1st floor. Neighbors should continue to expect wood panel deliveries over the next 2 months. Weekend work should be expected throughout the month of July an August.


Lastly, we are finishing excavation for our dry utility work along Mercy Street in the next couple of weeks. We intend to jump back over to California St. to perform the dry utility work needed there. Please be cautious of slower traffic speeds and consider other traffic routes if possible.


We hope these updates are helpful in keeping you informed about what’s happening onsite. For the latest updates, please visit the Project website at www.mountainviewlot12.org


Thank you for your patience while this work is underway and please reach out to me with any questions about ongoing operations. 


 

Best regards,

Christian Blevins

Assistant Project Manager

Related California Construction

Phone: 408-462-2407

 

P.S. If you received this via Wix Blog email notification and would like to unsubscribe, click the ‘unsubscribe’ link at the bottom of your email. And if you were forwarded this message and would like to be added to our mailing list, please visit the homepage at www.mountainviewlot12.org and submit the contact information form.

 
 

Alta Housing and Related California are equal opportunity housing providers and employers, dedicated to diversity, equity, and inclusion regardless of religion, sex, gender, national origin, disability, race, age, marital status, or sexual orientation.  

bottom of page